A delayed property settlement can have serious financial and practical consequences for buyers and sellers. But missing the settlement date may not automatically end the contract or mean the buyer loses their deposit. The parties’ rights depend on the contract, the reason for the delay and the state where the property is located.

Below we cover:
  • Why might settlement be delayed
  • Queensland specific
  • New South Wales specific
  • Victoria specific
  • Can the parties agree to extend settlement
  • What should you do if settlement may be delayed
  • How to reduce the risk of settlement delays

Why might settlement be delayed?

Common causes for delayed settlements include:

  • delays in loan approval or the lender releasing funds;
  • insufficient funds being available at settlement;
  • delays in discharging the seller’s mortgage;
  • difficulties completing an electronic settlement through PEXA;
  • unresolved title, caveat or registration issues;
  • a party failing to sign or return documents;
  • delays in a related purchase or sale; and
  • damage to the property or disputes arising before settlement.

Queensland

Under the standard REIQ residential contract, time is of the essence, and settlement deadlines must be strictly observed.

However, if clause 6.2 applies, either party can extend settlement without the other’s consent by giving written notice by 4pm QLD time on the settlement date. The new date cannot be more than five business days after the scheduled settlement date as defined in the contract. That limit is shared, not five days per party.

Separate rules may apply if a qualifying system outage or an event such as a flood prevents settlement. 

If the buyer can’t settle:

If the buyer misses the applicable deadline and the seller is ready, willing and able to settle, the seller may be able to terminate the contract without first giving the buyer more time. After valid termination, the seller may be able to keep the deposit and claim losses, such as a shortfall on resale. The seller may also be entitled to default interest on overdue amounts, but a valid extension under clause 6.2 does not, by itself, make the balance overdue.

If the seller can’t settle:

If the seller misses the applicable deadline and the buyer is ready, willing and able to settle, the buyer may be able to terminate the contract, recover the deposit and claim compensation.

If you still want the sale to go ahead:

Instead of ending the contract, either party may be able to keep it in place and seek specific performance, a court order requiring the other party to complete the sale. The court does not grant that order automatically.

New South Wales

In New South Wales, time is generally not of the essence for settlement, meaning that a missed settlement date usually does not give either party an immediate right to end the contract. Under the standard NSW contract, a party entitled to give a notice to complete can use it to set a new, strict deadline. Generally, the party serving the notice must be ready, willing and able to settle. The notice must allow a reasonable time.  Fourteen days is common but is not an automatic grace period – the contract, the circumstances and when the notice is served all matter.

If the buyer can’t settle:

The seller may be able to charge interest or recover the cost of issuing the notice if a special condition allows it. If the buyer misses the deadline in a valid notice to complete, the seller may be able to serve a separate termination notice, keep the deposit and seek compensation.

If the seller can’t settle:

The buyer may also be able to give a notice to complete. If the seller fails to comply and the buyer validly terminates, the buyer can generally recover the deposit and any other money paid under the contract and may be able to claim compensation.   

If you still want the sale to go ahead:

Instead of ending the contract, either party may be able to keep it in place and seek specific performance, a court order requiring the other party to complete the sale. The court does not grant that order automatically.

Victoria

A written default notice is usually required before either party can end the contract for a missed settlement. Under the commonly used LIV/REIV contract, the notice must explain what went wrong and generally give the party in default 14 days from when the notice is given to fix the problem and pay any reasonable costs and interest due under the contract. A notice can state that the contract will end if those requirements aren’t met. Without that wording, the contract does not automatically end when the notice period expires.

If the buyer can’t settle:

Default interest on the unpaid balance can accrue before the seller gives a notice. If the contract validly ends because of the buyer’s default, the seller may be able to keep or claim the deposit and seek compensation, including any recoverable shortfall on resale.

If the seller can’t settle:

The buyer may be able to give a default notice requiring the seller to complete the sale. If the contract validly ends under that notice, the buyer can generally recover the deposit and any other money paid under the contract, along with any interest and reasonable costs payable under the contract. The buyer may also be able to claim compensation for other losses.

If you still want the sale to go ahead:

Instead of ending the contract, either party may be able to keep it in place and seek specific performance, a court order requiring the other party to complete the sale. The court does not grant that order automatically. The contract’s default notice requirements should be checked before taking that step: a notice that automatically ends the contract may defeat the aim of enforcing it. 

Can the Parties Agree to Extend Settlement?

Yes. Even if neither party has a contractual right to extend settlement, the buyer and seller can generally agree to a new date. An extension agreement should address:

  • the revised settlement date;
  • whether interest or compensation for other costs (e.g. rescheduling of removalists or temporary accommodation expenses) is payable;
  • responsibility for additional legal costs;
  • how rates and other outgoings will be split; and
  • what happens if the new settlement date is missed.

A request for an extension is not an agreement and any informal conversation with an agent or other party should not be relied on as an effective extension. You should keep working towards the existing deadline unless the extension has been confirmed in writing or the deadline has changed under contractual or legislative provisions.

If the parties agree to early possession, allowing a buyer to move in prior to settlement, any such agreement should be in writing, including who is responsible for insurance, costs and damage.

What Should You Do if Settlement May Be Delayed?

If a delay is anticipated:

  1. Act before the deadline. Tell your solicitor what is holding up settlement, what still needs to happen and when the issue is likely to be resolved.
  2. Keep preparing to settle. Confirm what your lender or bank still needs, check that insurance remains in place and avoid locking in a new moving date before settlement is confirmed.
  3. Keep records of extra costs. Save receipts for removalist rebooking fees, storage or temporary accommodation. These costs are not automatically recoverable. It matters what the contract allows, what caused the expense and whether you took reasonable steps to keep it down.
  4. Be clear about whether you still want the sale to go ahead. Ending the contract and asking a court to enforce it are different options. Ending it too early or relying on an invalid notice can itself put you in breach.

What Should You Do if Settlement May Be Delayed?

Buyers and sellers can reduce the risk of delay by:

  • Buyers: Arrange finance early. Return signed loan documents promptly and, if applicable, confirm when your lender will be ready to release funds. Check how much you need to contribute and allow time for those funds to clear.
  • Sellers: Start the mortgage discharge process early. Flag any caveat or other title issue to your solicitor as soon as possible.
  • Both parties: Check that names and details match across documents, sign and return paperwork promptly, and review the settlement figures before settlement day. If another sale or purchase needs to settle first, flag that dependency early so the transactions can be coordinated.
If you think settlement might be delayed, raise it early so there’s time to resolve the issue or arrange an extension before the deadline. For settlement enquiries, contact MAP Lawyers: 
tel: 1300 680 584 
email: contact@maplawyers.com.au

* Current as at 20 November 2026. This article covers commonly used residential contracts. The contract edition, special conditions and rules for giving notices can change the outcome. Commercial, off-the-plan and other non-standard contracts may work differently.

MAP Lawyers logo

SELLING BUT NOT YET READY TO GET YOUR SELLER DISCLOSURE?

If you need a Queensland Seller Disclosure Form 2 but you are not quite ready to submit your request now, no problem. Please complete the information below and we will email you with the next steps when you are ready:

Seller Disclosure - Start Later Form

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Call Now Button